You can configure certain aspects of the Gantt chart display in Project Reporter
by adding the appropriate fields to views, as follows:
To display dependency links in a view, add either the Predecessors field or the
Successors field.
To display tracking Gantt bars, add the Baseline Start and Baseline Finish
fields.
To highlight critical tasks, add the Critical field to a Task view (and make
sure that you have selected an appropriate display color for critical tasks on
the Preferences page).